Work progress in November

17. november 2017

At the end of October was the beginning of assembly works for private house in Nordraaks vei, Oslo. Within 8 days the house was fully erected, despite heavy rain conditios on 2nd assembly day.

Now there are done roof finishing works and weatherboarding from the outside is about to be done as well soon.

A week after the first house was started, erection of twin house in Brumunddal had begun.  In total 860m2 were delivered. For roof constructions trusses were used, as that was more efficent solution this time.

In under  two weeks, the house elements were fully assembled including roof trusses. Now all the external finishings ar being installed at full speed. 

The third active project is a cabin, located in the beautifu ski resort Trysil. The progress on building site was noticable day by day. The weather conditions  for work were unpleasant – temperature stays below 0 and some days it was snowing. 

Nevertheless, assembly was done quite fast and this week we will finish works from our side. 

Looking forward to see the final result of each project!

 

Back

Signed contract for project Lindelia

12. october 2018

This week Husvik signing for a huge in-fill type project.

Production in September

18. september 2018

Progress in September

The Lodge Trysil assembling

18. july 2018

Climate wall assembly process for the Lodge Trysil project.

Gausdal Hytte

13. june 2018

One more cottage built in beautiful Gausdal area!