Work progress in November

17. november 2017

At the end of October was the beginning of assembly works for private house in Nordraaks vei, Oslo. Within 8 days the house was fully erected, despite heavy rain conditios on 2nd assembly day.

Now there are done roof finishing works and weatherboarding from the outside is about to be done as well soon.

A week after the first house was started, erection of twin house in Brumunddal had begun.  In total 860m2 were delivered. For roof constructions trusses were used, as that was more efficent solution this time.

In under  two weeks, the house elements were fully assembled including roof trusses. Now all the external finishings ar being installed at full speed. 

The third active project is a cabin, located in the beautifu ski resort Trysil. The progress on building site was noticable day by day. The weather conditions  for work were unpleasant – temperature stays below 0 and some days it was snowing. 

Nevertheless, assembly was done quite fast and this week we will finish works from our side. 

Looking forward to see the final result of each project!

 

Back

Husvik & Renewable Energy townhouses

19. february 2020

Husvik starts production for Ekerød - a renewable energy housing project that combines elaborate architecture and sustainable solutions to stay green on equipment.

Husvik handed the first two stages of construction at Hjeratunet.

11. february 2020

Husvik finally handed in February 2020 the last apartments of a total of 42 apartments at the Hjeratunet project. The first stages of construction on the Hjeratunet are the next sold out, now the third is laid out.

Prinsesseveien

7. october 2019

Husvik keep producing and delivering Prinsesseveien project, at the moment 14 of total 16 units are on site. Husvik team keep working!

SCANDIC BRENNEMOEN

13. september 2019

Husvik has been proud subcontractor, delivered and installed facade walls for SCANDIC BRENNEMOEN!​